US Capitol Power Plant: $85 million on one price outlook
total project cost committed on an analysis the agency's own Inspector General later said may have overstated the benefits.
In Washington, the Architect of the Capitol chose a 7.5 MW gas-turbine cogeneration plant: about $57 million in construction, $24 million in financing and $4 million in project management. The business case promised about $7.3 million in savings over 27 years. A plain gas boiler, at $9.3 million, would have saved about $2.7 million.
The US Government Accountability Office found that the agency "did not perform valid sensitivity or uncertainty analyses": gas and electricity prices were varied by a flat 25% with no rationale given. In 2019 the Inspector General concluded the analysis "may have overstated the financial benefits", partly because financing charges were understated and extra maintenance costs were not consistently included.