Power a data center the grid can't connect yet.

Interconnection queues run for years and large new loads are increasingly told there is no capacity. Sympheny sizes behind-the-meter generation, storage and a microgrid against your site's real hourly load, not a nameplate number, so you can move forward with a smaller, better-evidenced grid request and a case your investment committee can sign.

Full access for two weeks.

Sympheny Pareto front plotting life-cycle cost against CO2 emissions, each point an optimized data-center energy concept from the same project

Every on-site energy option on one chart: life-cycle cost against carbon, with the connection constraint held.

PROVEN ON EUROPEAN ENERGY & NETWORK PROJECTS

Trusted by energy planners, utilities and engineering firms

Used across Europe on feasibility, district energy and microgrid planning, where the goal was the same one a US data center has: needing less from the grid by generating, storing and sharing power on site. No US deployments are claimed.

IWBWSPEWZBuro HappoldIBC Chur

When data-center power planning gets hard

Multi-year interconnection queues and capacity that may never clear

AI and HPC load that swings sharply and drives the capacity charge

Behind-the-meter generation moving from optional to essential

Clean-power commitments and Scope 1, 2 and 3 scrutiny from tenants and lenders

Phasing on-site capacity against a grid connection that arrives late

Waste-heat offtake where a thermal energy network is next door

For developers and operators

  • Behind-the-meter and microgrid feasibility before site commitment
  • A smaller, defensible interconnection request
  • Clean-power and PPA pathway compared on cost and CO2
  • An investment case the board and lenders can interrogate

For the engineering partner

  • An optimized upstream concept ready for detailed design
  • Generation, storage, cooling and grid connection sized together
  • Staged investment against the load ramp and interconnection
  • Documented outputs that survive technical due diligence

How Sympheny helps

Size the microgrid against the real load, not a nameplate

Model PV, storage, gas, fuel cells and the cooling plant as one system against the site's real, variable load, including AI and HPC swings. The behind-the-meter system is justified by the load it serves and the grid capacity it avoids, which is what makes it bankable.

Shrink the interconnection request

Optimize generation, storage and load flexibility against capacity charges and connection limits, so the request to the grid is smaller and easier to approve. A smaller, well-evidenced connection is what actually moves through a multi-year queue.

A cost, carbon and resilience case in one model

The same model that sizes the system produces the Scope 1, 2 and 3 pathway and the resilience case, ready for the review where a lender, regulator or hyperscale tenant picks it apart. Directional estimates, traceable to the inputs.

What changes for data-center energy teams

Grid request
Before
A single large connection request sized on nameplate, then a multi-year wait with no plan B
After
A smaller request evidenced by an optimized behind-the-meter system that carries the gap
Load assumptions
Before
System sized on a flat average, wrong for real AI and HPC operation
After
Generation, storage and cooling sized against the real hourly load shape
Clean-power case
Before
Scope emissions assembled separately from the energy plan, by a different team
After
One model produces the power mix and the Scope 1, 2 and 3 pathway behind it
Investment sign-off
Before
The energy lead defends vendor numbers they didn't produce
After
Scenario outputs the CFO and lenders can interrogate, with sensitivities on price and load

Bring us a site the grid can't power yet.

Full access for two weeks.