Commonwealth Games 2010: power backup nobody compared
spent on DG sets, UPS and generator hire for the Games venues. The permanent DG sets went in without a cost-benefit analysis, CAG found.
For the 2010 Games, CPWD installed DG sets at five stadiums as permanent fixtures. At Jawaharlal Nehru Stadium it assessed the critical load at 10,065 kVA and installed 11,530 kVA of DG sets, plus 3,330 kVA of UPS. Across the venues, DG sets, UPS and hired generators came to ₹112.29 crore.
CAG found that CPWD "installed all DG Sets in all the five venues as permanent fixtures without any cost benefit analysis (permanent fixtures v/s hiring as and when required)", even though the consultant had suggested plug-in or permanent generators. It called the result "a massive 'overkill'" in October, a lean month for power demand, with an extra 100 MW allocated to Delhi for the Games. The prospects of using the sets after the Games, it said, were "negligible". CPWD replied that the configuration was meant to be finalised at technical sanction and that the plug-in option was intended for temporary overlays.